Adopt-A-Trail Reports
Maintenance run to 3N93 05/07/2011
I went up to Holcomb on Friday, 5/6 to do some clean up work on the trail. I sent the day cleaning up felled trees and removing some from the trail.
I spend a total of 8 hours on Friday.
Saturday, Chuck and Nick met with me at Fawnskin and we headed up to do some more tree removal. We spent all day working our way toward the middle rock garden, removing trees and moving rocks out of the trail as we found them.
All of the seeps are still flowing and at least water crossings are in need of repair. That will be taken care of at the next work weekend.
We spent a total of 12 hours each (including travel time).
Kurt- 20
Chuck-12
Nick-12
thanks for the help guys.